Structural Steel Erection & Fabrication

Structural Steel Erection & Fabrication

Back

What We Do

Our Approach

01

On-site Assembly and Installation

Structural steel for power plants, industrial buildings, and process facilities — from individual members through to large modular sections.

02

Rigging and Heavy Lifting

Crane operations for high-tonnage components including modular sections, trained riggers, and certified lifting procedures.

03

Sequencing and Coordination

Interface management with mechanical, electrical, and instrumentation scopes during plant build to maintain programme.

04

Safety Inspections and Compliance

Adherence to industry rigging, lifting, and erection standards with documented inspection and compliance records.

05

Pipe Rack Fabrication

Selective fabrication of pipe racks for industrial process piping infrastructure, delivered end-to-end with on-site erection.

06

ESP and Flue Gas Duct Fabrication

Fabrication of ESP hoppers and flue gas ductwork for power plant emissions control systems.

07

Cutting, Welding, and Assembly

Under certified welding procedures (AWS D1.1) with qualified welding personnel and full inspection documentation.

08

Surface Treatment and Coating

Painting, surface treatment, and modular fabrication where project-specific delivery requires off-site preparation.

Track Record

Where We've Delivered

Matarbari 2×600MW Coal Power Plant

17,000+ tons total
Bangladesh

Multi-scope structural steel campaign as part of the broader power plant build.

  • 5,000 tons of ESP hopper and flue gas duct fabrication
  • 7,000 tons of ESP structure and equipment erection
  • 3,000 tons of ash handling system structure and equipment erection
  • 1,500 tons of pipe rack fabrication, painting, shipping, and on-site erection
  • 1,100 tons across 11 storage tank erections
  • 480 tons of auxiliary boiler structure and equipment erection
Toshiba Plant System & Services CorporationDec 2021 – Dec 2023

2×1000MW Jimah East Power Plant

Port Dickson

Structural steel scope as part of the balance of plant works.

  • 300 tons of temporary site office structure design, fabrication, and installation
  • 350 tons across 3 storage tank erections
TPSC Engineering MalaysiaNov 2017 – Mar 2018

Standards & Compliance

Certifications & Codes

AWS D1.1 / BS

Welding Procedure Specifications

Certified welding personnel and procedures

Industry rigging and lifting safety standards

ISO 9001:2015

Quality Management for fabrication and erection