Matarbari Ultra Super Critical Coal Fired Power Plant
01
Project details
- 2×600 MW Coal Fired Power Plant
02
Duration
- 2018 – 2024
03
Work Description
- Construction Project Management
- Expatriate Management Services
- Manpower Supply
- Steam Turbine Generator (STG) Erection
- Mechanical Work – Turbine Erection
- Insulation, Roofing & Cladding
- Electrical & Instrumentation
- Balance Of Plant (BOP) Erection
- Substation, GIS and Transformer On-base and Testing
- Insulation, Roofing & Cladding
- Mechanical Work – Equipment
- Mechanical Work – Piping and Fire Fighting system
- Mechanical Work – Tank & Duct Erection
- Steel Structure Fabrication & Erection
- Industrial Services
- Machinery, Tools & Equipment Rental Services
- Scaffolding Service
- Project Cargo and Logistic Management